New Site Site Kick-off Meeting/Pre-con
1. Check and validate RTB/ARTB/SSDS data on actual site condition
2. Check and validate approved DDD on actual site condition
3. Check for possible discrepancy/variation on site (e.g. slope protection, hauling works, etc.)
4. Check for temporary power tapping point and water supply for construction purposes.
5. Validate coordinates
6. Accomplish site evaluation form/Skom Report
7. Validate site access, tempo facilities and safety on site.
Rebar and Concrete Pouring Inspection
1. Verify foundation bedding requirement.
2. Verify foundation thickness and dimension.
3. Inspection of rebar diameter, spacing and splicing requirements based on approved design prior to concrete pouring. Rebar condition should also be check, this should be ensure that are free from rust and oil. Mill certificate and tensile test result should be available.
4. Inspection of embedded and concealed works (Anchor bolts, Nuts and washers, Setting template)
5. Perform slump test and validate result of concrete cylinder samples
6. Monitor actual concrete pouring
7. Ensure safety compliance.
8. Accomplish rebar inspection and concrete pouring checklist.
RFTI Inspection
1. Inspection of facilities
  a. Tower - All tower components should be properly installed. Completeness and quality should be checked. Torque test should be performed.
  b. Concrete Pads - Should be constructed based on approved drawing. Location should be based on approved plans.
  c. Grounding System - should be properly installed and passed grounding test.
  d. Cable Ladders
2. Inspection of Power Facilities/Electical System. Tempo power should comply with approved engineering standards.
  a. MCB/MTS
  b. ACPDB
  c. Wires
  d. Generator
  e. Aviation light
3. Accomplish RFTI checklist

New Site Provisional Acceptance Test (PAT) for CME and TW
1. Ensure that Pre-PAT was performed by Vendor.
2. Check Pre-PAT docs and ensure that all documents provided are complete prior to schedule confirmation.
3. Perform all required test
  a. Tower verticality test
  b. Torque test
  c. Galvanization test
  d. Electrical and grounding test
     i. Earth resistance test
     ii. Wire insulation test
     iii. AC Power Distribution Test
  e. Grounding system
4. Voltage Standing Wave Ratio (VSWR) test (for feeder solution only)
5. CPRI Installation Inspection
6. BTS installation and commissioning
7. Antenna and RRU installation
8. Rectifier installation and commissioning
9. Environmental alarms simulation test
10. Verify as-built drawing vs approved plan vs actual
11. Complete other activities indicated in the PAT checklist
12. Accomplished PAT checklist.


Permanent Power Provisional Acceptance Test (PAT)
1. Ensure that Pre-inspection was performed by Vendor.
2. Check Pre-inspection report and ensure that all documents provided are complete prior to schedule confirmation.
3. Inspection of Permanent Power Facilities/Electical System.
  a. Transformer
  b. MCB/MTS
  c. ACPDB
  d. Wires
4. Verify as-built drawing vs approved plan vs actual
5. Complete other activities and test indicated in the PAT checklist
6. Accomplished PAT checklist.

Tower Retro Site Kick-off Meeting/Pre-con
1. Check and validate approved DDD on actual site condition
2. Check for possible discrepancy/variation on site (e.g. slope protection, hauling works, etc.)
3. Accomplish site evaluation form/Skom Report

Tower Retrofitting Provisional Acceptance (PAT)
1. Performs Nationwide Coordination and Scheduling of Tower retrofit Acceptance as agreed with Civil Works vendor and with GT- Field Ops when needed (SWAT Sites)
2. Ensures test results are within Globe and Industry standards
3. Material Testing
4. Approve Pouring request
5. Backfilling and Compaction test result
6. Dye Penetrant test result
7. Galvanizing results
8. Tower Verticality test result
9. Bolt Torque results
10. Guy Wire re-tensioning results

AC/DC Upgrade Provisional Acceptance Test (PAT)
1. Ensure that Pre-inspection was performed by Vendor.
2. Check Pre-inspection docs and ensure that all documents provided are complete prior to schedule confirmation.
3. Inspection of Permanent Power Facilities/Electical System.
  a. Transformer
  b. MCB/MTS
  c. ACPDB
  d. Wires
  e. Genset
  f. Rectifier
  e. Battery
4. Verify as-built drawing vs approved plan vs actual
5. Complete other activities and test indicated in the PAT checklist
6. Accomplished PAT checklist.


Materials Inventory Management
1. Warehouse inspection and delivery inventory
2. Review CDI and COC

Hello! we are
Jobayan
A simple way to connect candidates and companies

How does Jobayan work?

Publish your resume

Add your experience, education and skills. Jobayan will automatically match you with jobs.

Search Through Job Openings

Click "Apply Now" on a job opening and your contact details will automatically get sent to them.

Wait for a Match

Here in Jobayan, theres no forever in job hunting! When a job opening matches, you will be notified right away!

Get Started Now!
I want to hire

Your Career Awaits.